Lump sum vs cost-plus vs GMP contracts compared
Lump sum, cost-plus and GMP contracts differ in one thing above all: who pays if the job costs more than expected. In a lump sum contract the contractor agrees to one price and carries the overrun. In a cost-plus contract the owner pays the actual cost plus a fee and carries the overrun. A GMP contract is cost-plus with a ceiling: the owner pays cost plus fee up to a maximum, and the contractor carries cost above it.
Side by side
| Lump sum (stipulated sum) | Cost plus a fee | Cost plus a fee with a GMP | |
|---|---|---|---|
| Price set by | One agreed sum | Actual cost plus a fixed or percentage fee | Actual cost plus fee, up to a cap |
| Cost risk | Contractor | Owner | Owner below the cap, contractor above it |
| Design needed to price it | Complete | Little | Enough to set a cap, often before design is finished |
| Owner sees the books | Usually not | Yes | Yes |
| Savings below estimate | Contractor keeps them | Owner keeps them | As the contract says, often shared |
GMP stands for guaranteed maximum price. Unit price contracts are a fourth type, used when quantities are uncertain: the owner carries the quantity risk and the contractor carries the cost per unit.
Try one question
Question 1 of the free 10-question check on NASCLA Commercial. No signup. Then ask Seal, the AI study assistant, why the answer is right and the others are wrong.
Procurement and Contracting Requirements
A subcontractor on a bonded public project has not been paid for completed work. Which bond is meant to protect it?
Press A-D or 1-4 to choose an answer while this question is on screen.
Choose an answer to begin
One job priced three ways, with invented numbers
The estimated cost of a clinic fit-out is $2,000,000. In each case, test two outcomes: the job actually costs $1,950,000, or it actually costs $2,200,000.
Lump sum of $2,200,000. The owner pays $2,200,000 either way.
- At $1,950,000 of cost: the contractor earns 2,200,000 - 1,950,000 = $250,000.
- At $2,200,000 of cost: the contractor earns $0.
Cost plus an 8% fee on cost.
- At $1,950,000: fee 1,950,000 x 0.08 = $156,000, owner pays $2,106,000.
- At $2,200,000: fee 2,200,000 x 0.08 = $176,000, owner pays $2,376,000.
- Check: 1,950,000 x 1.08 = 2,106,000, and 2,200,000 x 1.08 = 2,376,000.
Cost plus 8% with a GMP of $2,250,000 and savings below the GMP shared 50/50. This invented contract counts the fee inside the GMP.
- At $1,950,000: cost plus fee is $2,106,000. Savings below the GMP: 2,250,000 - 2,106,000 = $144,000. Each side gets $72,000, so the owner pays 2,106,000 + 72,000 = $2,178,000, and the contractor earns 156,000 + 72,000 = $228,000.
- At $2,200,000: cost plus fee would be $2,376,000, above the cap. The owner pays $2,250,000, and the contractor absorbs 2,376,000 - 2,250,000 = $126,000. Its fee of $176,000 shrinks to 176,000 - 126,000 = $50,000.
- Check the first case: 2,178,000 - 1,950,000 = 228,000 to the contractor. Check the second: 2,250,000 - 2,200,000 = 50,000.
Real GMP contracts vary: some keep the fee fixed, some exclude it from the cap, and the split of savings is negotiated. Read the contract's definitions of cost of the work, fee and contingency.
Ask Seal before you buy AI your AI study assistant
See what's on the NASCLA Commercial exam, test yourself with 5 quick questions, or find the plan that fits you.
The NASCLA Commercial course
Available now · instant accessLearn all 12 subject areas and where to look in your books, then prove it on timed practice exams.
- 12modules of lessonsEvery task on the outline
- 4full-length timed exams115 questions in 330 minutes each
- 472practice questionsEach one explained
- 1week-by-week study planSet to your exam date
Turn a practice answer into a study step. In untimed practice, ask Seal AI about any question you answer, follow up, then see your weakest topics and what to drill next.
Instant access. Terms and refunds · Secure checkout by Stripe · Billed by Nori Software
Every answer comes with a full explanation.
How each one handles changes
In a lump sum contract, every scope change needs a change order with a price. Under cost-plus, the cost of added work flows through the books, though fee adjustments may still need agreement. Under a GMP, owner-requested scope changes raise the cap by change order, while the contractor's own contingency inside the GMP covers items like buyout gaps and minor coordination misses.
Delivery method is a separate question
Contract type is how the price is set. Delivery method is who contracts with whom: design-bid-build usually pairs with lump sum, while construction manager at risk often pairs with a GMP. The two ideas are often mixed up on exams.
Common mix-ups
- Thinking cost-plus has no risk for the contractor. Costs the contract does not define as reimbursable come out of the fee.
- Thinking a GMP is a lump sum. The owner still pays actual cost below the cap and audits the books.
- Confusing contract type with delivery method.
- Forgetting the fee grows with cost on percentage cost-plus. Owners use a fixed fee or a GMP to remove that incentive.
On the NASCLA exam
Contract types fall under Procurement and Contracting Requirements, 31 of the 115 scored questions. Construction Project Management is a listed reference that fits delivery methods and contract types, and the NASCLA Contractors Guide to Business, Law and Project Management covers contracts generally. Ask "who pays the overrun" first.
Practice it
Price the lump sum in the first place with markup vs margin, and see how a bid bond secures it in what is a bid bond. Cost-plus work depends on clean job costing. Contract time usually runs from the notice to proceed, and a lump sum is often billed against a schedule of values.
Take the free 10-question check
Start the free 10-question check. It is weighted to the twelve NASCLA subject areas, needs no signup and explains every answer, so you see which area to study first.
The NASCLA Commercial course has a lesson for each of the 12 subject areas that shows which listed reference to open and how to apply it, original practice questions with every answer worked, and four timed practice exams of 115 questions on a 330-minute clock. Your scores come back by subject area, so you know where the next study hour goes. See the course.
Not affiliated with or endorsed by NASCLA or PSI. NASCLA and PSI are named only to identify the exam and its test vendor.
Sources
Show the list
- PSI Candidate Information Bulletin 1458, content outline and reference list, updated 7 Jul 2026. Retrieved 5 Nov 2026.
- NASCLA Commercial Exam, NASCLA. Retrieved 5 Nov 2026.
Facts come from the sources listed above. If something has changed, tell us and we will correct it within 2 business days.
Your next step
Ready to see where you stand on NASCLA Commercial?
Free, untimed and scored by domain. No signup.
Start the free 10-question checkNASCLA Commercial course. Lessons, timed practice exams and a plan around your exam date. Get NASCLA Commercial course · $199 See the plans or read the free sample lesson.Terms and refunds
Want a timed run? Try the free 25-question mini-mock. The first 5 need no email.
Prefer paper? Free printables
- Print a class quiz (free PDF). 10 practice questions with an answer key on page 2.
- Print the flashcards as cut-out cards (free PDF). The free flashcard sample, ready to cut and carry.
From the blog
- Five estimating mistakes that cost points and money
- Over and under billing, walked through on the calculator
- Reading a surety's prequalification questionnaire