The Miller Act and state Little Miller Acts
The Miller Act is the federal law that requires contractors on federal construction to furnish a performance bond and a payment bond. It now sits in the U.S. Code at 40 U.S.C. 3131 to 3134, and the Federal Acquisition Regulation (FAR) carries it into federal contracts. Most states have their own laws for state and local public work, often called Little Miller Acts. Everything below about the federal act comes from the statute text and the FAR as we read them on 7 Nov 2026. Nothing here is legal advice.
Why public work needs it
On private work, an unpaid subcontractor or supplier can usually file a mechanics' lien against the property. Federal property cannot be liened. The payment bond gives those subs and suppliers something to claim against instead, and the performance bond protects the government if the contractor does not finish. See bid bond vs performance bond vs payment bond for how the three bonds differ.
What the statute requires
From 40 U.S.C. 3131, in our words:
- The bonds apply to contracts for the construction, alteration or repair of a public building or public work of the federal government, above a dollar threshold, and must be furnished before the contract is awarded.
- Performance bond: with a surety the contracting officer accepts, in an amount the officer considers adequate.
- Payment bond: for the protection of everyone supplying labor and material for the work. Its amount equals the total amount payable under the contract, unless the officer finds in writing that this is impractical and sets another amount. It may not be less than the performance bond.
The threshold. The statute text reads "more than $100,000". FAR 28.102-1, as shown on acquisition.gov on 7 Nov 2026, states the bond requirement for construction contracts exceeding $150,000. Federal acquisition thresholds are adjusted over time, so take the figure from the current FAR and the solicitation in front of you, not from a study guide. For smaller contracts, the statute (40 U.S.C. 3132) has the FAR provide alternative payment protections, and FAR 28.102-1 describes the contracting officer choosing among them for a lower band of contract values.
Try one question
Question 1 of the free 10-question check on NASCLA Commercial. No signup. Then ask Seal, the AI study assistant, why the answer is right and the others are wrong.
Procurement and Contracting Requirements
A subcontractor on a bonded public project has not been paid for completed work. Which bond is meant to protect it?
Press A-D or 1-4 to choose an answer while this question is on screen.
Choose an answer to begin
Who can claim on the payment bond
From 40 U.S.C. 3133, in our words:
- Someone with a contract directly with the prime contractor (a first-tier sub or supplier) who has not been paid in full within 90 days after its last labor or material may sue on the payment bond.
- Someone with a contract with a subcontractor but none with the prime (a second-tier sub or supplier) may sue only after giving the prime contractor written notice within 90 days from its last labor or material. The notice must state the amount claimed with substantial accuracy and who the labor or material was for, and be delivered by a method that gives third-party proof of delivery, or as a summons may be served.
- Further down the chain, the statute gives no right of its own. Courts have generally read it to stop at the second tier, so a supplier to a supplier is usually outside it.
Other points from the same section:
- Suit must be brought no later than one year after the claimant's last labor or material.
- It is brought in federal district court for the district where the contract was performed, in the name of the United States for the use of the claimant.
- A waiver of the right to sue on the payment bond is void unless it is in writing, signed by the claimant, and signed after the claimant has furnished labor or material for the work. A waiver signed in the subcontract before any work does not count.
- A claimant who swears it is unpaid can get a certified copy of the bond and contract from the agency.
Ask Seal before you buy AI your AI study assistant
See what's on the NASCLA Commercial exam, test yourself with 5 quick questions, or find the plan that fits you.
The NASCLA Commercial course
Available now · instant accessLearn all 12 subject areas and where to look in your books, then prove it on timed practice exams.
- 12modules of lessonsEvery task on the outline
- 4full-length timed exams115 questions in 330 minutes each
- 472practice questionsEach one explained
- 1week-by-week study planSet to your exam date
Turn a practice answer into a study step. In untimed practice, ask Seal AI about any question you answer, follow up, then see your weakest topics and what to drill next.
Instant access. Terms and refunds · Secure checkout by Stripe · Billed by Nori Software
Every answer comes with a full explanation.
A worked date count with invented dates
A second-tier supplier, selling to an electrical sub, makes its last delivery to a federal job on 10 March and is not paid.
- 90 days from 10 March: 21 days to the end of March, 30 in April, 31 in May, then 8 in June. 21 + 30 + 31 + 8 = 90, so the count lands on 8 June.
- Check by counting back: 8 June less 8 days is 31 May, less 31 is 30 April, less 30 is 31 March, less 21 is 10 March.
- Suit deadline: one year after the last delivery, 10 March of the next year.
Send the notice well before the last day. How a court counts the first and last day is a legal question, and late notice can lose the claim.
State Little Miller Acts
States have their own bond laws for state, county, city and school district work. They usually follow the same idea: payment and performance bonds on public contracts above a threshold, with claim rights for subs and suppliers. The thresholds, notice periods, who may claim, how far down the chain rights reach and the suit deadlines differ from state to state, and some local agencies add their own requirements. Read the statute and the bond for the project, and never carry one state's numbers to another.
Common mix-ups
- Filing a lien on federal property. The payment bond takes the place of lien rights.
- Quoting the threshold from memory. The statute text and the current FAR show different figures. Use the current FAR and the solicitation.
- Treating first and second tier the same. Only the second tier must give the 90-day written notice to the prime.
- Signing away bond rights before work starts. A waiver counts only if signed after furnishing labor or material.
- Assuming a state copies the federal rules. Each Little Miller Act is its own law.
On the NASCLA exam
The bulletin lists subject areas, not topics. We place bonds and public contracting under Procurement and Contracting Requirements, 31 of the 115 scored questions. The NASCLA Contractors Guide to Business, Law and Project Management fits by its title. Because the exam is used in many states, expect general principles rather than one state's deadlines.
Practice it
Read lien waivers for the private side of payment rights, and Davis-Bacon prevailing wage for the other federal rule that comes with federal construction.
Take the free 10-question check
Start the free 10-question check. It is weighted to the twelve NASCLA subject areas, needs no signup and explains every answer, so you see which area to study first.
The NASCLA Commercial course has a lesson for each of the 12 subject areas that shows which listed reference to open and how to apply it, original practice questions with every answer worked, and four timed practice exams of 115 questions on a 330-minute clock. Your scores come back by subject area, so you know where the next study hour goes. See the course.
Not affiliated with or endorsed by NASCLA or PSI. NASCLA and PSI are named only to identify the exam and its test vendor.
Sources
Show the list
- 40 U.S.C. 3131, Bonds of contractors of public buildings or works, Legal Information Institute. Retrieved 7 Nov 2026.
- 40 U.S.C. 3132, Alternatives to payment bonds provided by Federal Acquisition Regulation, Legal Information Institute. Retrieved 7 Nov 2026.
- 40 U.S.C. 3133, Rights of persons furnishing labor or material, Legal Information Institute. Retrieved 7 Nov 2026.
- FAR 28.102-1, General, acquisition.gov. Retrieved 7 Nov 2026.
- PSI Candidate Information Bulletin 1458, content outline and reference list, updated 7 Jul 2026. Retrieved 5 Nov 2026.
- The date example uses invented dates. State laws are described in general only.
Facts come from the sources listed above. If something has changed, tell us and we will correct it within 2 business days.
Your next step
Ready to see where you stand on NASCLA Commercial?
Free, untimed and scored by domain. No signup.
Start the free 10-question checkNASCLA Commercial course. Lessons, timed practice exams and a plan around your exam date. Get NASCLA Commercial course · $199 See the plans or read the free sample lesson.Terms and refunds
Want a timed run? Try the free 25-question mini-mock. The first 5 need no email.
Prefer paper? Free printables
- Print a class quiz (free PDF). 10 practice questions with an answer key on page 2.
- Print the flashcards as cut-out cards (free PDF). The free flashcard sample, ready to cut and carry.
From the blog
- Bidding public work for the first time
- Your first federal construction job: what changes
- Over and under billing, walked through on the calculator