Lien waivers: conditional vs unconditional

A lien waiver is a signed document in which a contractor, subcontractor or supplier gives up some or all of its mechanics' lien rights on a property, usually in exchange for a payment. Owners and lenders collect waivers so they know the people who did the work have been paid and cannot later claim against the property.

State law varies. Every state writes its own lien law. Some states prescribe the exact wording of each waiver and refuse to enforce other forms. Some make a waiver signed before payment, or a waiver of future rights in the contract, unenforceable. Others leave the form to the parties. The general terms below hold widely, but check the law where the property sits before you sign or rely on one.

The four common types

Waivers are sorted two ways: whether they depend on payment, and whether they cover one payment or the whole job.

Progress (partial)Final
ConditionalWaives rights for work through a stated date, but only once the stated payment is actually receivedWaives all rights on the job, but only once final payment is actually received
UnconditionalWaives rights for work through a stated date, effective when signedWaives all rights on the job, effective when signed

The safe sequence is to give a conditional waiver with the payment request and an unconditional waiver once the funds have cleared. An unconditional waiver signed before the check clears gives up the rights even if the check bounces.

Try one question

Question 1 of the free 10-question check on NASCLA Commercial. No signup. Then ask Seal, the AI study assistant, why the answer is right and the others are wrong.

Question 1 of 10 · free checkUntimed

Procurement and Contracting Requirements

A subcontractor on a bonded public project has not been paid for completed work. Which bond is meant to protect it?

Press A-D or 1-4 to choose an answer while this question is on screen.

Choose an answer to begin

What a careful waiver states

  • The property and project
  • Who is waiving and who is paying
  • The amount of the payment it is tied to
  • The through date the waiver covers
  • Any exceptions, such as unpaid retainage, disputed extra work or pending change orders

The exceptions matter. A progress waiver that does not carve out an unsigned change can waive the right to lien for that work.

Ask Seal before you buy AI your AI study assistant

See what's on the NASCLA Commercial exam, test yourself with 5 quick questions, or find the plan that fits you.

The NASCLA Commercial course

Available now · instant access

Learn all 12 subject areas and where to look in your books, then prove it on timed practice exams.

  • 12modules of lessonsEvery task on the outline
  • 4full-length timed exams115 questions in 330 minutes each
  • 472practice questionsEach one explained
  • 1week-by-week study planSet to your exam date

Turn a practice answer into a study step. In untimed practice, ask Seal AI about any question you answer, follow up, then see your weakest topics and what to drill next.

NASCLA Commercial course$199Get the course · $199

Instant access. Terms and refunds · Secure checkout by Stripe · Billed by Nori Software

Compare plans

Every answer comes with a full explanation.

A worked example with invented numbers

A framing subcontractor bills $48,000 for work through 31 March. The subcontract holds 10% retainage.

  • Retainage: 48,000 x 0.10 = $4,800
  • Payment due: 48,000 - 4,800 = $43,200
  • Check: 48,000 x 0.90 = 43,200

With the pay request, the sub gives a conditional progress waiver for $43,200 through 31 March, and lists the $4,800 retainage and a pending $2,150 change for added blocking as exceptions. When the $43,200 arrives and clears, the sub gives an unconditional progress waiver in the same amount and through date. Its lien rights for the retainage, the pending change and any work after 31 March stay open. At the end of the job, the sub trades a conditional final waiver for its final payment, then an unconditional final once it clears.

Waivers on public jobs

Public property generally cannot be liened. On public work, unpaid subs and suppliers usually look to the contractor's payment bond instead, under the federal Miller Act or the state's own law. Contracts may still ask for releases with each payment. See bid bond vs performance bond vs payment bond.

Common mix-ups

  • Signing an unconditional waiver to get paid. That gives up rights before the money is in hand.
  • Treating a waiver as a receipt only. It is a release of legal rights.
  • Forgetting the through date. Work after that date is not covered by the waiver.
  • Stating one state's deadlines or forms as the rule. Notice and filing deadlines, who may file, and waiver forms all differ by state. On an exam, an answer that says it depends on the state's law or the contract is often the right one.

On the NASCLA exam

Liens and waivers fall under Procurement and Contracting Requirements, 31 of the 115 scored questions. Because the exam serves many states, expect concepts (conditional vs unconditional, private vs public jobs) rather than one state's deadlines. Tab the liens topic in the NASCLA Contractors Guide to Business, Law and Project Management.

Practice it

Run the payment side in the retainage guide, and read pay-if-paid vs pay-when-paid for what happens when the owner does not pay the general contractor. Federal property cannot be liened, so subs on federal jobs claim on the payment bond instead; see the Miller Act and Little Miller Acts. Final waivers usually come in at closeout, after substantial completion and the punch list.

Take the free 10-question check

Start the free 10-question check. It is weighted to the twelve NASCLA subject areas, needs no signup and explains every answer, so you see which area to study first.

The NASCLA Commercial course has a lesson for each of the 12 subject areas that shows which listed reference to open and how to apply it, original practice questions with every answer worked, and four timed practice exams of 115 questions on a 330-minute clock. Your scores come back by subject area, so you know where the next study hour goes. See the course.

Not affiliated with or endorsed by NASCLA or PSI. NASCLA and PSI are named only to identify the exam and its test vendor.

Sources

Show the list

Facts come from the sources listed above. If something has changed, tell us and we will correct it within 2 business days.

Your next step

Ready to see where you stand on NASCLA Commercial?

Free, untimed and scored by domain. No signup.

Start the free 10-question check

NASCLA Commercial course. Lessons, timed practice exams and a plan around your exam date. Get NASCLA Commercial course · $199 See the plans or read the free sample lesson.Terms and refunds

Want a timed run? Try the free 25-question mini-mock. The first 5 need no email.

Prefer paper? Free printables

From the blog