Contractor job costing and overhead, worked out
Job costing is the practice of recording every cost against the job and cost code it belongs to, so each job's actual cost can be compared with its estimate while there is still time to act. Direct costs belong to one job: labor, materials, equipment and subcontracts. Overhead is the cost of running the company that no single job causes, such as office rent, office salaries and accounting, and it is spread across jobs at a rate.
Direct costs and labor burden
Each direct cost is coded to a job and a cost code, usually following the estimate's breakdown, so the budget and the actuals line up. Labor is the hardest to estimate and the easiest to lose money on, so it is tracked both in dollars and in hours or units installed.
A worker's wage is not the cost of the hour. Labor burden adds the employer's payroll taxes, workers' comp and liability premiums tied to payroll, and benefits. With an invented wage of $30.00 an hour and a burden of 35%:
- Burdened rate = 30.00 x 1.35 = $40.50 an hour
- Check: 35% of 30.00 is 10.50, and 30.00 + 10.50 = 40.50
Estimate and cost labor at the burdened rate, or the burden ends up uncovered.
Try one question
Question 1 of the free 10-question check on NASCLA Commercial. No signup. Then ask Seal, the AI study assistant, why the answer is right and the others are wrong.
Procurement and Contracting Requirements
A subcontractor on a bonded public project has not been paid for completed work. Which bond is meant to protect it?
Press A-D or 1-4 to choose an answer while this question is on screen.
Choose an answer to begin
Overhead and the overhead rate
General overhead is budgeted for the year, then recovered by adding a rate to each job. One common method spreads it over the year's planned direct cost.
Worked example with invented numbers. Annual overhead is budgeted at $420,000, and the company plans $3,500,000 of direct cost for the year.
- Overhead rate = 420,000 / 3,500,000 = 12% of direct cost
- Check: 3,500,000 x 0.12 = 420,000
A job with $180,000 of direct cost then prices like this, with profit at 8% on cost plus overhead:
- Overhead: 180,000 x 0.12 = $21,600
- Cost plus overhead: 180,000 + 21,600 = $201,600
- Profit: 201,600 x 0.08 = $16,128
- Bid: 201,600 + 16,128 = $217,728
- Check: 180,000 x 1.12 x 1.08 = 180,000 x 1.2096 = 217,728
If the company does less volume than planned, the same overhead is spread over fewer dollars of work and the real rate rises. At $2,800,000 of direct cost, the rate is 420,000 / 2,800,000 = 15%, and jobs priced at 12% under-recover. The free overhead rate calculator works this rate and the job bid for your own numbers, on direct cost or direct labor. Break-even revenue is the overhead divided by the gross profit percentage; the contractor financial ratios guide shows where gross profit comes from.
Ask Seal before you buy AI your AI study assistant
See what's on the NASCLA Commercial exam, test yourself with 5 quick questions, or find the plan that fits you.
The NASCLA Commercial course
Available now · instant accessLearn all 12 subject areas and where to look in your books, then prove it on timed practice exams.
- 12modules of lessonsEvery task on the outline
- 4full-length timed exams115 questions in 330 minutes each
- 472practice questionsEach one explained
- 1week-by-week study planSet to your exam date
Turn a practice answer into a study step. In untimed practice, ask Seal AI about any question you answer, follow up, then see your weakest topics and what to drill next.
Instant access. Terms and refunds · Secure checkout by Stripe · Billed by Nori Software
Every answer comes with a full explanation.
Reading a job cost report
A job cost report shows, for each cost code, the budget, the cost to date, the percent complete, and a projection to completion. Percent complete should come from the work in place, such as units installed, not from the money spent.
Worked example with invented numbers. The labor budget for a concrete wall is $60,000. $36,000 has been spent, and the crew has placed half the wall.
- Earned value of the work in place: 60,000 x 0.50 = $30,000
- Overrun so far: 36,000 - 30,000 = $6,000
- Projected cost at completion if the rate holds: 36,000 / 0.50 = $72,000
- Projected overrun: 72,000 - 60,000 = $12,000
- Check: the second half at the same rate costs another 36,000, and 36,000 + 36,000 = 72,000
Finding that at the halfway point, rather than at closeout, leaves time to change the crew, the method or the sequence, or to document a change order if the cause is a change.
Common mix-ups
- Pricing labor at the bare wage. Use the burdened rate.
- Measuring percent complete by money spent. That hides overruns until the end.
- Treating overhead as fixed per job. It is a company cost; the rate depends on volume.
- Putting job-site supervision in office overhead. Costs caused by one job, such as its superintendent and trailer, are usually job costs (often called general conditions), not company overhead.
On the NASCLA exam
Estimating, cost control and accounting fall under Procurement and Contracting Requirements, 31 of the 115 scored questions. Tab the estimating and accounting topics in the NASCLA Contractors Guide to Business, Law and Project Management, and cost control in Construction Project Management.
Practice it
Turn the bid into a margin in markup vs margin, and see how cost-plus contracts depend on clean job costing in lump sum vs cost-plus vs GMP. On covered federal work, the wage rates come from the wage determination; see Davis-Bacon prevailing wage. Find the sales volume that covers overhead with the free break-even calculator, and check a job on the WIP schedule with the over and under billing calculator, which finds percent complete by cost to cost.
Take the free 10-question check
Start the free 10-question check. It is weighted to the twelve NASCLA subject areas, needs no signup and explains every answer, so you see which area to study first.
The NASCLA Commercial course has a lesson for each of the 12 subject areas that shows which listed reference to open and how to apply it, original practice questions with every answer worked, and four timed practice exams of 115 questions on a 330-minute clock. Your scores come back by subject area, so you know where the next study hour goes. See the course.
Not affiliated with or endorsed by NASCLA or PSI. NASCLA and PSI are named only to identify the exam and its test vendor.
Sources
Show the list
- PSI Candidate Information Bulletin 1458, content outline and reference list, updated 7 Jul 2026. Retrieved 5 Nov 2026.
- NASCLA Commercial Exam, NASCLA. Retrieved 5 Nov 2026.
Facts come from the sources listed above. If something has changed, tell us and we will correct it within 2 business days.
Your next step
Ready to see where you stand on NASCLA Commercial?
Free, untimed and scored by domain. No signup.
Start the free 10-question checkNASCLA Commercial course. Lessons, timed practice exams and a plan around your exam date. Get NASCLA Commercial course · $199 See the plans or read the free sample lesson.Terms and refunds
Want a timed run? Try the free 25-question mini-mock. The first 5 need no email.
Prefer paper? Free printables
- Print a class quiz (free PDF). 10 practice questions with an answer key on page 2.
- Print the flashcards as cut-out cards (free PDF). The free flashcard sample, ready to cut and carry.
From the blog
- Pricing overhead on small construction jobs
- When to hire an estimator: signs and the math
- Subcontractor buyout without bid shopping