Bid shopping and bid peddling in construction
Bid shopping and bid peddling are two sides of the same habit: reopening subcontract prices after the general contractor's bid is in. Bid shopping is when the general contractor takes the low sub price it carried in its bid and shows it, or hints at it, to other subs to get a lower number. Bid peddling is when a sub that lost, or did not bid, approaches the general contractor after bids close and offers to beat the price it carried. Both are widely treated as unethical. Whether either is illegal depends on the job and the place.
Why the industry frowns on them
- Subs price defensively. A sub that expects to be shopped holds back its best number on bid day, so the general contractor's bid ends up higher, not lower.
- Confidential prices leak. A sub's quote is its own business information. Showing it to a competitor breaks trust.
- Quality and safety suffer. A sub squeezed after award looks for savings in labor, supervision and materials.
- Good subs stop bidding to you. A reputation for shopping shrinks the bid list.
Try one question
Question 1 of the free 10-question check on NASCLA Commercial. No signup. Then ask Seal, the AI study assistant, why the answer is right and the others are wrong.
Procurement and Contracting Requirements
A subcontractor on a bonded public project has not been paid for completed work. Which bond is meant to protect it?
Press A-D or 1-4 to choose an answer while this question is on screen.
Choose an answer to begin
Shopping is not the same as buyout
After award, a general contractor has to buy out the job: sign every subcontract and purchase order. Fair buyout includes:
- confirming each sub's scope line by line, so nothing falls between trades
- correcting a sub's clear mistake, or letting the sub withdraw it
- agreeing on schedule, insurance, bonds and payment terms
- negotiating a real scope change, such as an owner-accepted alternate or value engineering
What makes it shopping is using one sub's price as a lever on another for the same scope.
Ask Seal before you buy AI your AI study assistant
See what's on the NASCLA Commercial exam, test yourself with 5 quick questions, or find the plan that fits you.
The NASCLA Commercial course
Available now · instant accessLearn all 12 subject areas and where to look in your books, then prove it on timed practice exams.
- 12modules of lessonsEvery task on the outline
- 4full-length timed exams115 questions in 330 minutes each
- 472practice questionsEach one explained
- 1week-by-week study planSet to your exam date
Turn a practice answer into a study step. In untimed practice, ask Seal AI about any question you answer, follow up, then see your weakest topics and what to drill next.
Instant access. Terms and refunds · Secure checkout by Stripe · Billed by Nori Software
Every answer comes with a full explanation.
Where rules apply
- Subcontractor listing. Some public owners, and some states for public work, require bidders to name their major subs in the bid and restrict substituting them afterward. These laws exist partly to stop shopping. Which jobs they cover, and the rules for substitution, differ by state.
- Bid depositories. In some regions, sub bids go through a depository with set rules on timing and use. Participation is local and voluntary.
- Sub bound, general contractor free. In many states, courts have held a sub to the price it gave when the general contractor relied on it in its own bid, under a doctrine called promissory estoppel. The general contractor is not usually bound to use that sub. That one-sided result is a big part of why subs resent shopping.
A worked example with invented numbers
On bid day, a general contractor carries $1,100,000 of sub prices in a $1,450,000 bid.
What shopping can look like. After award, it takes the low drywall price of $212,000 to a second sub and gets $198,000.
- Saving: 212,000 - 198,000 = $14,000
- As a share of the drywall price: 14,000 / 212,000 = 6.6%, rounded
Check: 212,000 x 0.066 = 13,992, close to 14,000 after rounding.
What it can cost. If subs who know this general contractor shops add 3% to their bid-day prices as a cushion:
- Added to the bid: 1,100,000 x 0.03 = $33,000
- New bid: 1,450,000 + 33,000 = $1,483,000
Check: 33,000 / 1,100,000 = 0.03, and 1,483,000 - 1,450,000 = 33,000.
The $14,000 won on one trade after award is less than half the $33,000 the cushion adds across all trades on bid day (14,000 / 33,000 is about 0.42), and the higher bid may lose the job to begin with. The 3% is invented. The point is the direction, not the size.
How to bid it clean
- Ask for prices on a clear scope sheet, so quotes are comparable.
- Level the bids on bid day: adjust each quote for exclusions and inclusions, then pick.
- Tell bidders the rules up front: one price, used as given.
- Award to the sub you carried unless there is a scope, qualification or bond problem you can name.
- Do not share one sub's number with another.
Common mix-ups
- Calling all post-award negotiation shopping. Fixing scope gaps or pricing real changes is buyout.
- Assuming it is illegal everywhere. On private work it is mostly an ethics and reputation problem. Listing laws apply only where a state or owner adopts them.
- Mixing the two terms. Shopping is done by the general contractor; peddling is done by the sub.
On the NASCLA exam
The bulletin lists subject areas, not topics. We place bidding practice and ethics under Procurement and Contracting Requirements, 31 of the 115 scored questions. Construction Project Management and the NASCLA Contractors Guide to Business, Law and Project Management fit by their titles, so tab their bidding topics.
Practice it
Level two invented sub quotes and check the markup on the result with markup vs margin. Read what is a bid bond for the general contractor's own promise on bid day.
Take the free 10-question check
Start the free 10-question check. It is weighted to the twelve NASCLA subject areas, needs no signup and explains every answer, so you see which area to study first.
The NASCLA Commercial course has a lesson for each of the 12 subject areas that shows which listed reference to open and how to apply it, original practice questions with every answer worked, and four timed practice exams of 115 questions on a 330-minute clock. Your scores come back by subject area, so you know where the next study hour goes. See the course.
Not affiliated with or endorsed by NASCLA or PSI. NASCLA and PSI are named only to identify the exam and its test vendor.
Sources
Show the list
- PSI Candidate Information Bulletin 1458, content outline and reference list, updated 7 Jul 2026. Retrieved 5 Nov 2026.
- NASCLA Commercial Exam, NASCLA. Retrieved 5 Nov 2026.
- All examples use invented numbers. Listing laws and court doctrines are described in general; each state's law decides the details.
Facts come from the sources listed above. If something has changed, tell us and we will correct it within 2 business days.
Your next step
Ready to see where you stand on NASCLA Commercial?
Free, untimed and scored by domain. No signup.
Start the free 10-question checkNASCLA Commercial course. Lessons, timed practice exams and a plan around your exam date. Get NASCLA Commercial course · $199 See the plans or read the free sample lesson.Terms and refunds
Want a timed run? Try the free 25-question mini-mock. The first 5 need no email.
Prefer paper? Free printables
- Print a class quiz (free PDF). 10 practice questions with an answer key on page 2.
- Print the flashcards as cut-out cards (free PDF). The free flashcard sample, ready to cut and carry.
From the blog
- Bidding public work for the first time
- Subcontractor buyout without bid shopping
- Construction closeout without the last-month scramble