Change orders in construction: how to price one
A change order is a written agreement, signed by the owner and the contractor, that changes the contract's scope of work, contract sum, contract time or a mix of them. Once signed, it becomes part of the contract. Work done on a verbal request, without a change order or other written authority, puts the contractor's payment at risk.
Three ways a change gets made
Most construction contracts give the owner the right to change the work without voiding the contract, through some version of these:
- Change order. Owner and contractor agree on the scope, the price and the time, and both sign.
- Construction change directive. The owner orders the work before price or time are agreed, so the job does not stop. The contractor proceeds, keeps detailed records, and the price is settled later by the method the contract sets.
- Minor change. The architect or engineer orders a small change that does not affect price or time, such as moving an outlet a few inches.
The names differ between contract forms, but the idea is the same: separate the order to do the work from the agreement on what it costs.
Try one question
Question 1 of the free 10-question check on NASCLA Commercial. No signup. Then ask Seal, the AI study assistant, why the answer is right and the others are wrong.
Procurement and Contracting Requirements
A subcontractor on a bonded public project has not been paid for completed work. Which bond is meant to protect it?
Press A-D or 1-4 to choose an answer while this question is on screen.
Choose an answer to begin
Where changes come from
Owner requests, design errors and omissions, RFI answers that turn out to add work, differing site conditions, code-driven changes required at plan review or inspection, and owner-caused delays. A change can also be constructive: the owner's conduct, such as insisting on a costlier method than the documents require, changes the work without anyone calling it a change. Contractors protect themselves by giving written notice promptly.
Ask Seal before you buy AI your AI study assistant
See what's on the NASCLA Commercial exam, test yourself with 5 quick questions, or find the plan that fits you.
The NASCLA Commercial course
Available now · instant accessLearn all 12 subject areas and where to look in your books, then prove it on timed practice exams.
- 12modules of lessonsEvery task on the outline
- 4full-length timed exams115 questions in 330 minutes each
- 472practice questionsEach one explained
- 1week-by-week study planSet to your exam date
Turn a practice answer into a study step. In untimed practice, ask Seal AI about any question you answer, follow up, then see your weakest topics and what to drill next.
Instant access. Terms and refunds · Secure checkout by Stripe · Billed by Nori Software
Every answer comes with a full explanation.
Notice matters
Contracts set a time limit for giving written notice of a change or claim, often counted in days from when the contractor knew or should have known. Missing it can waive the claim, however valid the extra cost. Track every potential change in a log the day it comes up.
Pricing a change
The contract usually says how. Common methods are a lump sum quoted for the change, unit prices already in the contract, or cost plus a stated percentage for overhead and profit. Many contracts cap the markup on changes and say whether the general contractor may mark up its subcontractors' change pricing, and by how much. Deductive changes, where work is removed, produce a credit to the owner, and contracts often limit or exclude profit on a credit.
A worked example with invented numbers
The owner asks for an added door and frame in a corridor wall. The contract allows 15% overhead and profit on the direct cost of changes, and the contractor asks for 2 extra days.
- Labor: 32 hours x $45.00 burdened rate = $1,440
- Material: $2,860
- Equipment rental: $400
- Direct cost: 1,440 + 2,860 + 400 = $4,700
- Overhead and profit: 4,700 x 0.15 = $705
- Change order amount: 4,700 + 705 = $5,405
Check: 4,700 x 1.15 = 5,405.
Updating the contract sum:
| Line | Amount |
|---|---|
| Original contract sum | $1,250,000 |
| Net change by earlier change orders | $18,400 |
| This change order | $5,405 |
| New contract sum | $1,273,805 |
Check: 1,250,000 + 18,400 = 1,268,400, and 1,268,400 + 5,405 = 1,273,805. The schedule of values on the next payment application gets a new line for the change, and the contract time moves by the 2 days only if the change order says so.
Common mix-ups
- Treating a change directive as a change order. A directive orders the work. The price and time may still be open.
- Doing the work on a phone call. Without written authority, the contractor may have no right to be paid.
- Pricing time last. Ask for the days in the same change order. Many contracts treat a signed change order with no time as full settlement of the change.
- Marking up as though overhead were free. Use the contract's allowed markup, not your bid markup. See markup vs margin.
On the NASCLA exam
Changes appear in Procurement and Contracting Requirements (the contract side, 31 of 115 questions) and General Requirements (the field paperwork side, 25 of 115). Tab the contracts topic in the NASCLA Contractors Guide to Business, Law and Project Management, and the changes topic in Construction Jobsite Management.
Practice it
Add the change to a pay application in the retainage guide, then see how lump sum vs cost-plus vs GMP contracts treat changes differently. When the change comes from ground that differs from the contract documents, see differing site conditions, and when it adds days, see how time ties to liquidated damages.
Take the free 10-question check
Start the free 10-question check. It is weighted to the twelve NASCLA subject areas, needs no signup and explains every answer, so you see which area to study first.
The NASCLA Commercial course has a lesson for each of the 12 subject areas that shows which listed reference to open and how to apply it, original practice questions with every answer worked, and four timed practice exams of 115 questions on a 330-minute clock. Your scores come back by subject area, so you know where the next study hour goes. See the course.
Not affiliated with or endorsed by NASCLA or PSI. NASCLA and PSI are named only to identify the exam and its test vendor.
Sources
Show the list
- PSI Candidate Information Bulletin 1458, content outline and reference list, updated 7 Jul 2026. Retrieved 5 Nov 2026.
- NASCLA Commercial Exam, NASCLA. Retrieved 5 Nov 2026.
Facts come from the sources listed above. If something has changed, tell us and we will correct it within 2 business days.
Your next step
Ready to see where you stand on NASCLA Commercial?
Free, untimed and scored by domain. No signup.
Start the free 10-question checkNASCLA Commercial course. Lessons, timed practice exams and a plan around your exam date. Get NASCLA Commercial course · $199 See the plans or read the free sample lesson.Terms and refunds
Want a timed run? Try the free 25-question mini-mock. The first 5 need no email.
Prefer paper? Free printables
- Print a class quiz (free PDF). 10 practice questions with an answer key on page 2.
- Print the flashcards as cut-out cards (free PDF). The free flashcard sample, ready to cut and carry.
From the blog
- Excusable, compensable and concurrent delay explained
- The 31 NASCLA procurement questions: where the points are
- When to hire an estimator: signs and the math