Five estimating mistakes that cost points and money
The same five estimating mistakes lose money on real bids and points on the NASCLA Commercial General Building exam. On a job, they show up as a thin or negative margin months later. On the exam, they show up as a wrong option that looks right, because the person who wrote the distractor made the mistake on purpose. Each one below has a worked example with invented numbers, checked a second way. Estimating sits mostly in Procurement and Contracting Requirements, the largest area at 31 of 115 questions. To see how you do on this kind of question, take the free 10-question check.
1. Using markup as if it were margin
Markup is profit as a percentage of cost. Margin is the same dollars as a percentage of the selling price. They are not the same number.
Worked example. Direct cost is $180,000 and the company needs a 12% margin.
- Right: price = 180,000 / (1 - 0.12) = 180,000 / 0.88 = $204,545.45. Check: 204,545.45 x 0.88 = 180,000.00.
- Wrong: price = 180,000 x 1.12 = $201,600. That is a 12% markup, which is only a 10.71% margin. Check: 21,600 / 201,600 = 0.1071, and 0.12 / 1.12 = 0.1071.
The slip costs $2,945.45 (204,545.45 - 201,600) on one job. On an exam question, $201,600 makes a ready-made wrong option.
Fix: before you multiply, ask "percent of what?" Cost means markup. Price means margin.
Try one question
Question 1 of the free 10-question check on NASCLA Commercial. No signup. Then ask Seal, the AI study assistant, why the answer is right and the others are wrong.
Procurement and Contracting Requirements
A subcontractor on a bonded public project has not been paid for completed work. Which bond is meant to protect it?
Press A-D or 1-4 to choose an answer while this question is on screen.
Choose an answer to begin
2. Mixing units
The classic is a concrete slab with the thickness left in inches.
Worked example. A slab is 60 ft by 40 ft and 6 in thick.
- Right: 6 in = 0.5 ft. Volume = 60 x 40 x 0.5 = 1,200 cubic feet. In cubic yards: 1,200 / 27 = 44.44 cy. Check: 27 x 44 = 1,188, and the remaining 12 / 27 = 0.44, so 44.44 cy.
- Wrong, inches as feet: 60 x 40 x 6 = 14,400 cubic feet, or 533.33 cy, twelve times too much.
- Wrong, cubic feet priced as yards: 1,200 "yards" is 27 times too much.
Fix: convert every dimension to the same unit before you multiply, and write the unit next to every number. A cubic yard is 27 cubic feet because it is 3 x 3 x 3.
3. Adding waste twice, or not at all
Waste belongs in the estimate once, stated as a percentage, on the quantity it applies to.
Worked example. The slab above needs 44.44 cy, and the estimator allows 5% waste. Order quantity = 44.44 x 1.05 = 46.67 cy. Check: 5% of 44.44 is 2.22, and 44.44 + 2.22 = 46.66; the last hundredth is rounding (unrounded, 44.444 x 1.05 = 46.667). Round up to the next whole or half yard your supplier sells.
Two ways to get it wrong:
- Twice: waste added at takeoff and again on the summary sheet. 5% then 5% again is 1.05 x 1.05 = 1.1025, a 10.25% allowance, not 10% and not 5%.
- Never: the net takeoff priced as if not a yard is lost. A no-waste total makes an easy wrong option.
Fix: keep waste in its own column so you can see it once.
4. Pricing labor at the bare wage
The wage is not what an hour of labor costs. Payroll taxes, insurance and benefits, called labor burden, go on top.
Worked example. A carpenter earns $32 an hour and burden is 35% of wages. Burdened rate = 32 x 1.35 = $43.20. Check: 35% of 32 is 11.20, and 32 + 11.20 = 43.20.
A task needs 120 crew hours:
- Burdened: 120 x 43.20 = $5,184.
- Bare wage: 120 x 32 = $3,840.
The gap is $1,344. Check: 120 x 11.20 = 1,344.
Fix: build the burden into the hourly rate before you multiply by hours. On the exam, read whether the stem gives you a wage or a burdened rate.
5. Missing an addendum or a general-conditions cost
Addenda change the bid documents before bids are due. Miss one, and you may price the wrong scope. On many bid forms, failing to acknowledge an addendum can make the bid nonresponsive.
The quieter version is missing what the general and supplementary conditions add: bonds, insurance, temporary facilities, cleanup, a schedule requirement. None of it shows on the drawings, and all of it costs money.
Fix: read the front end before the drawings, list every addendum on the bid form, and keep a checklist of general-conditions items. Reading a bid package like an examiner walks through the order.
Why these five make good exam questions
Each mistake produces a specific wrong number, and that makes a believable wrong option. When your answer matches an option, ask whether a common slip would land on a neighbor. If two options differ by a factor of 27, 12 or 1.0something, one of them is a trap.
Practice them
Take the free 10-question check. It needs no signup and explains every answer, including the arithmetic. For a lesson on Procurement and Contracting with more worked examples and practice questions where every answer is worked, see the plans. The procurement post shows where estimating sits in that area. Free calculators help with the unit and waste slips: board feet, drywall sheets and cut and fill. The cash flow example shows what a priced job does to the bank balance, and the subcontractor buyout post covers locking in sub prices after award.
Sources
- PSI Candidate Information Bulletin 1458, content outline and question counts, updated 7 Jul 2026. Retrieved 5 Nov 2026.
- All examples use invented numbers.
FAQ
What is the difference between markup and margin?
Markup is profit as a percentage of cost. Margin is profit as a percentage of price. A 12% markup is about a 10.71% margin.
How many cubic feet are in a cubic yard?
27, because a cubic yard is 3 ft x 3 ft x 3 ft.
What is labor burden?
The employer's costs on top of the wage, such as payroll taxes, insurance and benefits, usually expressed as a percentage of wages.
Related guides
Free tools for this topic
Keep reading
Your next step
Ready to see where you stand on NASCLA Commercial?
Free, untimed and scored by domain. No signup.
Start the free 10-question checkNASCLA Commercial course. Lessons, timed practice exams and a plan around your exam date. Get NASCLA Commercial course · $199 See the plans or read the free sample lesson.Terms and refunds
More free practice
- Read a free lesson
- Take the free 25-question timed test
- Question of the day
- Free flashcards
- Print a class quiz (free PDF)
- Print the flashcards as cut-out cards (free PDF)
The free check and the course are on the NASCLA Commercial page.