Markup and margin calculator

Turn a cost estimate into a bid price. Enter the direct cost, your overhead as a percent or a dollar figure, and your profit as either a markup or a margin. The calculator shows the bid price and states the profit both ways, so you can see how far apart the two percentages are.

Bid price from cost

Direct cost
$120,000.00
Overhead
$14,400.00
Total cost (direct + overhead)
$134,400.00
Bid price = total cost × (1 + 10%)
$147,840.00
Profit
$13,440.00
Profit as markup on total cost
10%
Profit as margin of the bid price
9.09%
Overhead and profit as markup on direct cost
23.2%
Overhead and profit as margin of the bid price
18.83%

Using 10% as a margin instead would bid $149,333.33, $1,493.33 higher.

Markup is a percentage of cost. Margin is the same dollars as a percentage of the selling price. Every rate here is your own input, so take overhead from your books and profit from your own target.

Studying for NASCLA Commercial? Take the free 10-question check to see exactly which topics to fix first, then close the gaps with the Bid Bond course.

Or read a full free lesson first (no signup).

This is covered in Procurement, contracting and running the business of the Bid Bond course.

Studying with a coworker? Send them the free check.

The formula: markup versus margin

Markup and margin describe the same dollars of profit against two different bases. Markup measures profit against cost. Margin measures it against the selling price. Because the price is bigger than the cost, the margin percent is always smaller than the markup percent for the same job.

  • Total cost = direct cost + overhead. Overhead entered as a percent is that percent of direct cost.
  • Price with a markup = total cost × (1 + markup).
  • Price with a margin = total cost ÷ (1 − margin).
  • Margin = markup ÷ (1 + markup), and markup = margin ÷ (1 − margin). A 10% markup is a 9.09% margin; a 10% margin is an 11.11% markup.

The calculator also states overhead and profit together, against direct cost and against the price, because some estimates quote one combined figure. When a question layers the steps (overhead on cost, then profit on cost plus overhead), apply each percent to the running total, as the calculator does.

Worked example 1: overhead as a percent, profit as a markup

Direct cost is $120,000, overhead is 12% of direct cost and profit is a 10% markup. These are invented study numbers.

  1. Overhead = 120,000 × 0.12 = $14,400. Total cost = 120,000 + 14,400 = $134,400.
  2. Bid price = 134,400 × 1.10 = $147,840. Profit = 147,840 − 134,400 = $13,440.
  3. Margin = 13,440 ÷ 147,840 = 9.09%. Check with the formula: 0.10 ÷ 1.10 = 0.0909.
  4. Overhead and profit together are 14,400 + 13,440 = $27,840, which is 23.2% of direct cost and 18.83% of the price.

Check the whole chain another way: 120,000 × 1.12 × 1.10 = 147,840.

Worked example 2: overhead in dollars, profit as a margin

Direct cost is $250,000, overhead is $30,000 and the target is a 10% margin.

  1. Total cost = 250,000 + 30,000 = $280,000.
  2. Bid price = 280,000 ÷ 0.90 = $311,111.11. Profit = $31,111.11.
  3. Check: 311,111.11 × 0.90 = 280,000.00, and 31,111.11 ÷ 311,111.11 = 10%.
  4. As a markup on total cost that profit is 31,111.11 ÷ 280,000 = 11.11%.

The trap: marking up $280,000 by 10% gives $308,000, which is $3,111.11 below the price that earns a 10% margin. These are original arithmetic examples, not exam questions.

Markup and margin questions

Why is my margin lower than my markup?

Both divide the same profit, but margin divides it by the price and markup divides it by the cost. The price is the larger number, so the margin percent comes out smaller.

Should overhead go on direct cost or on the price?

Do what your estimate or the question says. This calculator puts an overhead percent on direct cost and then applies profit to cost plus overhead. If a question applies them differently, follow its order.

Where is this on the NASCLA exam?

The Bid Bond course teaches markup, margin and bid pricing in its Procurement and Contracting Requirements lesson. That is the largest of the twelve subject areas on the NASCLA outline, with 31 of the 115 scored questions.

See the NASCLA exam outline for all twelve subject areas and their question counts.

Add overhead to direct cost, then apply profit as a markup on cost or a margin of the price, with every step shown. A study and estimating aid; your own books and your contract set the real rates.

Try one free question

Try one question

Question 1 of the free 10-question check on NASCLA Commercial. No signup. Then ask Seal, the AI study assistant, why the answer is right and the others are wrong.

Question 1 of 10 · free checkUntimed

Procurement and Contracting Requirements

A subcontractor on a bonded public project has not been paid for completed work. Which bond is meant to protect it?

Press A-D or 1-4 to choose an answer while this question is on screen.

Choose an answer to begin

Free NASCLA Commercial study plan

A week-by-week plan from today to your exam, weighted to the published exam outline. We show it here and email you a copy.

Ask Seal before you buy AI your AI study assistant

See what's on the NASCLA Commercial exam, test yourself with 5 quick questions, or find the plan that fits you.

Sources

From the blog

Practice NASCLA estimating questions

You just priced a bid with markup and margin. The free 10-question NASCLA Commercial check scores you across the subject areas in minutes, needs no signup and explains every answer. The Bid Bond course drills the rest.

Take the free 10-question check

The NASCLA Commercial course

Available now · instant access

The NASCLA Commercial course

  • 12modules of lessonsEvery task on the outline
  • 4full-length timed exams115 questions in 330 minutes each
  • 472practice questionsEach one explained
  • 1week-by-week study planSet to your exam date

Turn a practice answer into a study step. In untimed practice, ask Seal AI about any question you answer, follow up, then see your weakest topics and what to drill next.

NASCLA Commercial course$199

Terms and refunds · Secure checkout by Stripe · Billed by Nori Software

See the course

Compare plans

Every answer comes with a full explanation.

By the Bid Bond editorial team. Report an error.