CPM float calculator

Schedule a small network by the critical path method. Enter each activity with an ID, a duration and the activities that must finish before it starts. The calculator runs the forward and backward passes and shows early and late dates, total float, free float and the critical path.

Activities

Forward pass gives ES and EF; backward pass from 17 gives LF and LS. Total float = LS − ES. Free float = earliest ES of the successors − EF.
ActivityDurationESEFLSLFTotal floatFree floatCritical
A4040400Yes
B641041000Yes
C34781140No
D51015101500Yes
E4711111544No
F21517151700Yes
Project duration
17 days
Critical path
A-B-D-F
Critical activities (zero total float)
A, B, D, F

Durations are in days, or any one unit you use throughout. Predecessors are activity IDs separated by commas; leave them blank for a starting activity. Links are finish to start with no lag, and the first activity starts at day 0.

Studying for NASCLA Commercial? Take the free 10-question check to see exactly which topics to fix first, then close the gaps with the Bid Bond course.

Or read a full free lesson first (no signup).

This is covered in General requirements and your reference map of the Bid Bond course.

Studying with a coworker? Send them the free check.

The method: forward pass, backward pass, float

The critical path method finds the longest chain of dependent activities. That chain sets the shortest time the whole project can take. This calculator counts elapsed days from 0, the convention the Bid Bond lesson uses.

  • Forward pass: early start (ES) is the largest early finish (EF) of the predecessors, or 0 with none. EF = ES + duration.
  • Backward pass: late finish (LF) is the smallest late start (LS) of the successors, or the project finish with none. LS = LF − duration.
  • Total float = LS − ES (or LF − EF): how long an activity can slip without moving the project finish.
  • Free float = earliest ES of the successors − EF: how long it can slip without moving any later activity.
  • Activities with zero total float are critical. Free float is never more than total float.

Worked example 1: six activities

A takes 4 days. B (6 days) and C (3 days) follow A. D (5 days) follows B. E (4 days) follows C. F (2 days) follows both D and E. These are invented study numbers and the calculator's starting example.

  1. Forward pass: A 0 to 4, B 4 to 10, C 4 to 7, D 10 to 15, E 7 to 11. F starts at the later of 15 and 11, so F runs 15 to 17.
  2. Backward pass from 17: F 15 to 17, D 10 to 15, E 11 to 15, B 4 to 10. C must finish by E's late start of 11, so C runs 8 to 11. A must finish by the earlier of B's 4 and C's 8, so A runs 0 to 4.
  3. Total float: C = 8 − 4 = 4 days, E = 11 − 7 = 4 days, and A, B, D and F have 0.
  4. Free float: C = 7 − 7 = 0, because any slip in C delays E; E = 15 − 11 = 4.
  5. Critical path: A-B-D-F, 17 days.

Check by paths: A-B-D-F is 4 + 6 + 5 + 2 = 17 days and A-C-E-F is 4 + 3 + 4 + 2 = 13 days. The difference, 17 − 13 = 4, is the float shared by C and E.

Worked example 2: shorter float

The same logic with new durations: A 3, B 5, C 2, D 4, E 6 and F 3 days.

  1. Forward pass: A 0 to 3, B 3 to 8, C 3 to 5, D 8 to 12, E 5 to 11, F 12 to 15.
  2. Backward pass from 15: F 12 to 15, D 8 to 12, E 6 to 12, B 3 to 8, C 4 to 6, A 0 to 3.
  3. Total float: C = 4 − 3 = 1 day and E = 6 − 5 = 1 day. Free float: C = 5 − 5 = 0 and E = 12 − 11 = 1.

Check by paths: A-B-D-F is 3 + 5 + 4 + 3 = 15 and A-C-E-F is 3 + 2 + 6 + 3 = 14, a difference of 1 day. C and E share that one day: if C slips a day, E has none left. These are original arithmetic examples, not exam questions. The CPM scheduling and float guide walks through the same network.

CPM float questions

How do you find total float and free float?

Run a forward pass for the early dates and a backward pass for the late dates. Total float is late start minus early start. Free float is the earliest early start of the following activities minus this activity's early finish. In the worked example, activity C has 4 days of total float but 0 free float, because any slip in C delays E.

How do I find the critical path?

The critical path is the chain of activities with zero total float, and it is the longest path through the network. In the worked example A-B-D-F takes 4 + 6 + 5 + 2 = 17 days and A-C-E-F takes 4 + 3 + 4 + 2 = 13, so A-B-D-F is critical and the project takes 17 days.

Why does the first activity start at day 0?

This calculator, like the Bid Bond lesson, counts elapsed days from 0, so early finish = early start + duration and a successor starts the day its predecessor finishes. Some books count the first day as day 1. The floats and the critical path come out the same either way; only the start and finish labels shift.

Where is this on the NASCLA exam?

The Bid Bond course teaches CPM scheduling and float in its General Requirements lesson. General Requirements is one of the twelve subject areas on the NASCLA outline, with 25 of the 115 scored questions.

See the NASCLA exam outline for all twelve subject areas and their question counts.

Forward pass for early start and finish, backward pass for late start and finish, then total float, free float and the critical path, with every date shown. A study and scheduling aid; finish-to-start links only, with no lags or calendars.

Try one free question

Try one question

Question 1 of the free 10-question check on NASCLA Commercial. No signup. Then ask Seal, the AI study assistant, why the answer is right and the others are wrong.

Question 1 of 10 · free checkUntimed

Procurement and Contracting Requirements

A subcontractor on a bonded public project has not been paid for completed work. Which bond is meant to protect it?

Press A-D or 1-4 to choose an answer while this question is on screen.

Choose an answer to begin

Free NASCLA Commercial study plan

A week-by-week plan from today to your exam, weighted to the published exam outline. We show it here and email you a copy.

Ask Seal before you buy AI your AI study assistant

See what's on the NASCLA Commercial exam, test yourself with 5 quick questions, or find the plan that fits you.

Sources

Practice NASCLA scheduling questions

You just ran a forward and backward pass. The free 10-question NASCLA Commercial check scores you across the subject areas in minutes, needs no signup and explains every answer. The Bid Bond course drills the rest.

Take the free 10-question check

The NASCLA Commercial course

Available now · instant access

The NASCLA Commercial course

  • 12modules of lessonsEvery task on the outline
  • 4full-length timed exams115 questions in 330 minutes each
  • 472practice questionsEach one explained
  • 1week-by-week study planSet to your exam date

Turn a practice answer into a study step. In untimed practice, ask Seal AI about any question you answer, follow up, then see your weakest topics and what to drill next.

NASCLA Commercial course$199

Terms and refunds · Secure checkout by Stripe · Billed by Nori Software

See the course

Compare plans

Every answer comes with a full explanation.

By the Bid Bond editorial team. Report an error.